JUNE 15, 2009
THE MAHONING TOWNSHIP AUTHORITY
HELD THE MONTHLY MEETING ON JUNE 15,2009 AT 7:00PM IN
THE MAHONING TOWNSHIP MUNICIPAL BUILDING LOCATED AT 1101
BLOOM RD., DANVILLE, PA. 17821.
THOSE PRESENT FOR THE MEETING
WERE:
THOMAS MERTZ EDWARD
DRAUGELIS
DAVID BARRON GRIER
BOEDKER
OPERATOR BRET LEVAN
SECRETARY LUCY HETTINGER
PUBLIC
RICHARD CAMPBELL (DELINQUENCY)
ROBERT BOMBOY
BUD BREECH
PUBLIC
RICHARD CAMPBELL HAD WATER TURNED
OFF 7 YEARS AGO FOR NON PAYMENT. MR. CAMPBELL REQUESTS
WATER TO BE TURNED ON , NO METER AT PRESENT ON PROPERTY.
METER MUST BE PURCHASED AND INSTALLED BEFORE ANY WATER
IS TURNED ON. PAYMENT ARRANGEMENT WILL BE TAKEN UNDER
LEGAL ADVISE.
MR. BOMBOY QUESTIONS THE ARTICLE IN
THE PRESSS ENTERPRISE. NEWSPAPER ARTICLE AND PICTURES
TAKEN ON RED LANE ARE INCLUDED WITH THESE MINUTES.
THE MINUTES OF MAY 18,2009 WERE
APPROVED AS READ. UNANIMOUS
OPERATORS REPORT
WATER REPORT WAS READ AND APPROVED
MOTION TO ACCEPT MADE BY DAVE BARRON SECOND ED DRAUGELIS
UNANIMOUS
VALVE WAS REPLACED ON LOCUST ST.
PLEASANT ST. LINE REPLACEMENT ON
HOLD UNTIL STREET DEPARTMENT IS AVAILABLE
SIKORA HAS FINAL PUNCHLIST TO
COMPLETE PROJECT.
SOLICITORS REPORT
RESOLUTION 220 IMPOSING A $50.00
TRANSFER FEE EFFECTIVE JULY 1, 2009WAS PRESENTED. MOTION
TO ACCEPT MADE BY ED DRAUGELIS SECOND GRIER BOEDKER
UNANIMOUS
OLD BUSINESS
T & S UPDATED PLANS PER ARRO’S
REVIEW. NEW PLANS ARE NOW UNDER REVIEW.
WOODS OF WELSH
NO PERMITS WILL BE ISSUED BY
MAHONING TOWNSHIP UNTIL DEP VIOLATIONS ARE HANDLED.
MAHONING TOWNSHIP WILL NOT ISSUE SEWER AND WATER PERMITS
FOR WOODS OF WELSH DEVELOPMENT AT THIS TIME. MOTION TO
HOLD PERMITS MADE BY DAVE BARRON SECOND ED DRAUGELIS
UNANIMOUS
DISCUSSION OF POSSIBLE OAK ST
EXTENSION PROJECT WAS ENTERTAINED. ESTIMATED COST FOR
PROJECT WILL BE REQUESTED TO THE ARRO CONSULTANTS.
REPLACEMENT OF SEWER AND PARTIAL
WATER LINES, REPAVE.
PRICES NOT TO EXCEED REQUESTED FROM
ARRO BEFORE PROCEEDING.
MOTION DAVE BARRON SECOND ED
DRAUGELIS UNANIMOUS
I AND I REPORT
REVIEWED
DELINQUENCY REPORT
REVIEWED
THE MAHONING TOWNSHIP AUTHORITY IS
REQUESTING THAT THE MONTOUR COUNTY COMMISSIONERS HOST A
SEWER SUMMIT MEETING AS SOON AS POSSIBLE.
LETTER ATTACHED
UNANIMOUS
FOCUS SHEET
MOTION TO ACCEPT DAVE BARRON SECOND
GRIER BOEDKER UNANIMOUS
TIME OFF SHEET
MOTION TO APPROVE DAVE BARRON
SECOND GRIER BOEDKER UNANIMOUS
ALL BILLS PREVIOUSLY PAID AND PAID
NOW REVIEWED
ARRO SUBMITTED LETTER TO APPROVE
SIKORA BILL CONTINGENT UPON RECEIVING ALL PAPERWORK.
AMOUNT TO BE PAID IS $148,133.99.
MOTION TO ACCEPT PAYMENT OF BILLS.
MOTION TO APPROVE MADE BY GRIER BOEDKER SECOND
DAVE BARRON UNANIMOUS
CONVENE TO EXECUTIVE SESSION
LEGAL ISSUES
RECONVENE
BOARD DISCUSSED THE CAMPBELL
PROPERTY WITH THE SOLICITOR
METER MUST BE INSTALLED, PAYMENT TO
BE MADE AS FOLLOWS:
1.
METER PAYMENT
2.
½ OF OUTSTANDING UTILITY BILL CLEARS BANK
3.
WATER TURNED ON
4.
IN 45 DAYS SECOND PAYMENT HALF OF REMAINING
INCLUDING NEW BILL
5.
IN 45 DAYS REMAINING PAYMENT INCLUDING ANY NEW
BILL
6.
IF THIS ARRANGEMENT NOT MET THE WATER WILL BE
SHUT OFF AFTER THE 45 DAY PERIOD.
GRIER BOEDKER MOTIONED PAYMENT
ARRANGEMENT DAVE BARRON SECONDS UNANIMOUS
:ATTACHED NEWSPAPER ARTICLE AND
PICTURES
ADJOURNMENT