Tom questioned the bill for their sewer.
The Board told him to come back in a year and they will
re-visit their account.
Minutes of July 19, 2010 were read and approved. Unanimous.
Outstanding delinquent list reviewed
Woods of Welsh tank drain was discussed
today with Dale Heckman, Bret Levan and Jim Stein.
Jim was advised of the work to be done. He
told the Project Manager that the work would be started the
week of August 23, 2010.
Stamey and Schepis will have sewer lines
repaired. Tentative dates, the last week of August by Elijah
Evans.
Televising and cleaning of sewer lines done
by Sewer Specialties, payment was recommended by Dale
Heckman, Project Manager. Report will follow.
Operators report
Water use increased. Motion to approve
report made by Ed Draugelis, second Grier Boedker.
Unanimous
Paving Proposals for Montgomery Village and Red Lane
stations
After discussion, Grier Boedker made the
option to accept the quote of $7400.00 from Gutelius to pave
the Montgomery Village station. Ed Draugelis seconded the
motion. Unanimous.
Telemetry computer needs an upgrade. PSC has
made a quote of $3795.00. Grier Boedker motioned that we
upgrade the telemetry computer. Dave Barron seconded the
motion. Unanimous.
Solicitors report
Rick reviewed the Letter of Credit for the Keyser
development. The document is correct.
I and I report and Focus report
Motion to approve both made by Dick Jordan,
second Dave Barron. Unanimous
Time off sheet approved. Motioned Dave Barron, second Ed
Draugelis. Unanimous
All bills approved for payment. Unanimous
Paying on line or auto pay discussed.
Grier Boedker motioned to re-visit in a year.
Dave seconded the motion. Unanimous
Adjournment